Correct Answer - Option 1 : 16 days
Given:
A can finish \(\frac{2}{5}\) of a task in 12 days and B can finish\(\frac{2}{3}\) of the same task in 30 days.
Calculation:
A's 1 day's work = 2/5 × 1/12 = 1/30
B's 1 day's work = 2/3 × 1/30 = 1/45
(A + B)'s 1 days work = 1/30 + 1/45 = 1/18
(A + B)'s 10 days work = 10 × 1/18 = 5/9
Remaining work = 1 - 5/9 = 4/9
C's 1 day's work = 4/9 × 1/16 = 1/36
(B + C)'s 1 day's work = 1/45 + 1/36 = 9/180 = 1/20
∴ B and C will complete 4/5th work in = 4/5 × 20 = 16 days.
Time taken by person to complete a/b fraction of work = a/b × (Number of days in which person alone can complete work)