Correct Answer - Option 3 : 12 days
Given:
A can finish \(\frac 3 5\) of a task = 6 days
B can finish \(\frac 2 3\) of the same task = 12 days
A and B worked together = 5 days
C alone completed the remaining task = 8 days
Concept Used:
If a man can do a work in t days then in 1 day he will do 1/t part of the work
Calculation:
A alone can finish task = 6 × (5/3)
⇒ 10 days
B alone can finish task = 12 × (3/2)
⇒18 days
⇒ A and B worked for 5 days = (5/10) + (5/18)
⇒ (45 + 25) /90 = 70/90
⇒ 7/9
⇒ Remaining work = 1 - (7/9)
⇒ 20/90 = 2/9
2/9th of work completed by C = 8 days
C alone can finish task = 8 × (9/2) = 36 days
⇒ B + C working together can do in 1 day = 1/18 + 1/36
⇒ (2 + 1)/36 = 3/36 = 1/12
In one day B and C together can complete = 1/12 of the task
B and C together can complete a task = 12 day
∴ The number of days taken to complete a task B and C together is 12