Correct Answer - Option 4 : 6 days
Given:
P = 2Q
Q = 3R
R can complete a work in 54 days
Concept used:
If A does a work in n days then 1-day work of A is 1/n
Calculation:
According to question
Let, P's one day work = 6 unit
⇒ Q's one day work = 3 unit
⇒ R's one day work = 1 unit
R can complete work in 54 days
⇒ Total work = 1 × 54 = 54 unit
⇒ (P + Q) can complete work in = 54/( 6 + 3)
⇒ 54/9
⇒ 6 days
∴ P and Q together can complete work in 6 days