Ram and Sham can complete the work in 4.5 days. Ram is thrice efficient as Sham. In how many days Sham can complete the work?
1. 10 days
2. 20 days
3. 18 days
4. 12 days
5. 9 days

1 Answer

0 votes
by (237k points)
selected by
 
Best answer
Correct Answer - Option 3 : 18 days

Given:

Let Ram's and Sham's 1 day's work be 1/a and 1/b respectively.

⇒ 1/a + 1/b = 1/4.5

⇒ 1/a + 1/b = 10/45 = 2/9

Then,

⇒ b = 3a

Solving,

a = 6 and b = 18

∴ Sham will complete work in 18 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.