Correct Answer - Option 2 : 85 days
GIVEN:
B's efficiency = 2 × A's efficiency
C's efficiency = 3 × A's efficiency
time taken by (B + C) = 17 days
FORMULA USED:
work = efficiency × time
CALCULATION:
let A's efficiency = x
∴ B's efficiency = 2x
C's efficiency = 3x
work done by (B + C) = 17 × 5x = 85x
∴ time taken by A alone = 85x /x = 85 days