A can do a particular work in 6 days. B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?
1. Rs. 500
2. Rs. 600
3. Rs. 450
4. Rs. 350
5. Rs. 400

1 Answer

0 votes
by (240k points)
selected by
 
Best answer
Correct Answer - Option 5 : Rs. 400

Given:

 The 

Amount of work A can do in 1 day = 1/6
Amount of work B can do in 1 day = 1/8
Calculation:
Amount of work A + B can do in 1 day = 1/6 + 1/8 = 7/24
Amount of work A + B + C can do in 1 day = 1/3
Amount of work C can do in 1 day = 1/3 - 7/24 = 1/24
Work done by A in 1 day : work done by B in 1 day : work done by C in 1 day

1/6 : 1/8 : 1/24 = 4 : 3 : 1
Amount to be paid to C = 3200 × (1/8) = Rs.400

∴ The amount to be paid to C is Rs. 400.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.