Two men and 7 children complete a certain piece of work in 4 days while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is 

(a) 60 days 

(b) 15 days 

(c) 6 days 

(d) 51 days

Please log in or register to answer this question.

1 Answer

+1 vote
by (53.1k points)

(b) 15 days

(2 Men + 7 Children)'s 1 days' work = \(\frac{1}{4}\)

(4 Men + 4 children)'s 1 days' work = \(\frac{1}{3}\)

\(\Rightarrow\) 2M + 7C = \(\frac{1}{4}\) ............(i)

4M + 4C = \(\frac{1}{3}\) ...............(ii)

Now we can solve the value of man.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...