In a project activity for completion, if the most optimistic time is 4 days, most likely time is 6 days & most pessimistic time is 11 days, then the Expected time shall be:
1. 5.5 days 
2. 6.5 days
3. 8 days
4. 7 days

1 Answer

0 votes
by (102k points)
selected by
 
Best answer
Correct Answer - Option 2 : 6.5 days

Concept:

The PERT (Project Evaluation and Review Technique) technique is used, when activity time estimates are stochastic in nature. For each activity, three values of time (optimistic, most likely, pessimistic) are estimated.

  • Optimistic time (to) estimate is the shortest possible time required for the completion of an activity
  • Most likely time (tm) estimate is the time required for the completion of activity under normal circumstances
  • Pessimistic time (tp) estimate is the longest possible time required for the completion of an activity


In PERT expected time of an activity is determined by using the below-given formula:

  \({t_e} = \frac{{\left( {{t_o} + 4{t_m} + {t_p}} \right)}}{6}\)

Calculation:

 Given,

 optimistic time (to) = 4 days, most likely time (tm) = 6 days

 pessimistic time (tp) = 11 days

   \({t_e} = \frac{{\left( {{t_o} + 4{t_m} + {t_p}} \right)}}{6}\)

  \(t_e = \frac{{4\ +\ \left( 4\times{{6}} \right) +\ 11}}{6}\)

   te = 6.5 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.