If Lj = the latest occurrence time for event j,

Ei = the earliest occurrence time for event i,

Tij = the duration of activity \( \overrightarrow{ij}\),

What is the total float for activity \( \overrightarrow{ij}\)?


1.

Ei – Lj Tij


2. Lj – Ei - Tij
3. Tij – Ei - Lj
4. Tij – Lj + Ei"

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 2 : Lj – Ei - Tij

Explanation:

Total floats is the maximum amount of time an activity can be delayed without delaying project.

Total floats calculated separately for each activity.

FT = Maximum available time – Activity time

FT = (Lj - Ei) - Tij

∴ FT = Lj - Ej - Tij

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.