Correct Answer - Option 1 : 6 days
Concept:
Project Evaluation and Review Technique (PERT) is probabilistic in nature and is based upon three-time estimates to complete an activity.
Optimistic Time (to): It is the minimum time that will be taken to complete an activity if everything goes according to the plan.
Pessimistic Time (tp): It is the maximum time that will be taken to complete an activity when everything goes against the plan.
Most likely time (tm): It is the time required to complete a project when an activity is executed under normal conditions.
Average or most expected time is given by \({t_E} = \left( {\frac{{{t_p}\; + \;4{t_m}\; + {t_o}}}{6}} \right)\)
Calculation:
Given:
Pessimistic Time (tp) = 10 days, Most likely time (tm) = 6 days, Optimistic Time (to) = 2 days
Average or most expected time is given by
\({t_E} = \left( {\frac{{{t_p}\; + \;4{t_m}\; + {t_o}}}{6}} \right)\)
\({t_E} = \left( {\frac{{{10}\; + \;4\times{6}\; + {2}}}{6}} \right)=6\;days\)