Duration along the critical path defines which of the following?

A. Shortest duration needed

B. Shortest duration permissible

C. Longest duration needed

D. Longest duration permissible

Select the code for the correct answer from the options given below: 


1. A and B only 
2. A and D only 
3. B and C only 
4. C and D only

1 Answer

0 votes
by (95.4k points)
selected by
 
Best answer
Correct Answer - Option 2 : A and D only 

Concept

The critical path is the sequence of activities that represents the longest path through a project. It determines the shortest possible project duration.

Critical path can be easily determined with the help of total float calculations. The activities on the critical path are those activities that have total float equal to zero.

Statement A & D are correct.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.