X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is:
1. 15 days
2. 20 days
3. 30 days
4. 10 days

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 2 : 20 days

Given:

X can do a piece of work = 25 days

Percentage increase in efficiency (a) = 25%

Calculation:

X’s one day work = 1/25

Y’s one day work = X’s one day’s work × (100 + a)/100

Y’s one day work

⇒ (1/25) × (100 + 25)/100

⇒ (1/25) × 125/100

⇒ 1/20

Y alone takes 20 days.

∴ The number of days taken by Y is 20 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.