Correct Answer - Option 3 : Rs. 10800
Given:
Anita and Batuk undertake a project worth = Rs. 27000
Anita alone can do the work = 10 days
Calculation:
Anita can do 10% of work in a day.
Anita has worked 6 days in total. And so, has Batuk.
Anita completed 60% work in 6 days and Batuk did 40% of the work in 6 days
Efficiency of Anita and Batuk = 6 : 4
∴ Batuk’s share = 4/10 × 27000
⇒ 4 × 2700
⇒ Rs. 10800
The share of Batuk in the earnings is Rs. 10800.