Processing times on a single machine for 3 jobs are given below. All the jobs are available at time t = 0.

Job

1

2

3

Processing time
(minute)

15

3

6


The mean flow time (in minute) as per the shortest processing time (SPT) sequence is _______.

1 Answer

0 votes
by (106k points)
selected by
 
Best answer

Concept: 

Shortest processing time: In the SPT rule, jobs are sequenced in increasing order of their processing time i.e. minimum time first and maximum time in last. Note: If two jobs have the same process time then job having less due date will be processed first.

Calculation:

Given:

The jobs are to be scheduled using the shortest processing time (SPT) sequence.

Job

Processing times
(minutes)

Flow time
(minutes)

2

3

3

3

6

6 + 3 = 9

1

15

15 + 9 = 24


∴ The total flow time = 3 + 9 + 24 = 36 minutes

∴ The mean flow time = 36/3 = 12 minutes

∴ The mean flow time as per the shortest processing time (SPT) sequence is 12 minutes.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.