The excess of minimum available time over activity duration is called


1. total float
2. free float
3. independent float
4. None of the above

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : independent float

Explanation:

Float:

(i) It is associated with activity times.

(ii) It is analogous to the slack of events in PERT.

(iii) It is the range within which the start or finish time of activity may fluctuate without affecting the project completion time.

(iv) Floats are of the following types:

1. Total float: The time span by which starting or finishing of an activity can be delayed without delaying the completion of the project. Total float of activity affects total float of succeeding as well as preceding activities. 

2. Free float: The delay can be made without delaying succeeding activities. It affects only preceding activities.

3. Independent Float: It is the minimum excess available time which exists without affecting any of succeeding or preceding activities.

4. Interfering Float: It is similar to head event slack.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.